Homebuyer secured Rs 1.36 crore refund with 10.20% interest after RERA ruled in his favour, but builder challenged the order nearly 5 years later citing a Supreme Court ruling; why Bombay High Court dismissed the plea
You buy a flat and due to some dispute with the real estate developer, you seek a refund and the Real Estate Regulation Authority (RERA)’s adjudicating officer passes an order in your favour. Years later, the developer challenges the order on the basis of a fresh Supreme Court ruling. What happens then?The Bombay High Court has dismissed a petition filed by a real estate developer which sought to set aside an order directing it to refund Rs 1.36 crore, along with interest at 10.20% per annum, to a flat purchaser.The developer argued that a subsequent Supreme Court ruling had rendered the original refund order legally invalid.The Bombay High Court rejected the developer’s plea and declined to reopen an order that had attained finality after the developer failed to challenge it within the prescribed statutory period. Read on to know what happened.
What the case is about
The dispute arose from an order in 2019, passed by an adjudicating officer of the Maharashtra Real Estate Regulatory Authority. The officer had directed the real estate developer to refund Rs 1,35,99,246 paid by a flat buyer, along with interest at 10.20% per annum until realisation.The real estate developer did not challenge the order within the prescribed statutory period for filing an appeal. Following non-compliance, a recovery order was issued in October 2021. Under the applicable mechanism, recovery of amounts ordered to be refunded under RERA could be pursued as arrears of land revenue under the Maharashtra Land Revenue Code, 1966.Meanwhile in November 2021, the Supreme Court delivered its judgment in Newtech Promoters and Developers Pvt. Ltd. v. State of Uttar Pradesh, which interpreted provisions of RERA concerning the powers of the regulatory authority and its adjudicating officers.The real estate developer subsequently argued that the ruling undermined the legal basis of the 2019 refund order. Its contention was that an adjudicating officer appointed under Section 71 of RERA could adjudicate compensation claims but could not direct a refund. On that basis, the developer sought to have both the original order and the subsequent recovery order set aside.The developer also relied on a Bombay High Court Division Bench judgment in Marveledge Realtors Pvt. Ltd. v. State of Maharashtra, delivered on September 13, 2024, as well as other judicial decisions.The homebuyer opposed the petition. His counsel argued that the original order had attained finality because the developer had not filed a statutory appeal. He also pointed to the delay in approaching the High Court: although the Supreme Court had delivered its judgment in November 2021, the developer filed the present writ petition only in August, 2024.
Why Bombay High Court ruled in favour of homebuyer
The Bombay High Court first examined whether the Supreme Court’s judgment in Newtech established that an adjudicating officer could never be entrusted with the power to direct a refund.The court distinguished the issue decided by the Supreme Court from the question before it.The court noted that Newtech dealt with whether a whole-time member of the regulatory authority could order a refund, rather than whether the authority could delegate that function to an adjudicating officer under Section 81 of RERA.“The Supreme Court was not dealing with a contention that the Adjudicating Officer could be delegated the power to direct a refund,” the judgment said.The court further explained that the Supreme Court’s observations had to be read in the context of the issue it had actually decided.The judgement said: “Seen in that light, in Newtech, the Supreme Court essentially held that the WTM can indeed exercise the power to direct a refund. The Supreme Court did not at all venture into what the Adjudicating Officer cannot do.”The High Court concluded that delegating the exercise of refund powers to an adjudicating officer was not contrary to RERA’s statutory scheme. It distinguished refund claims, which can involve a summary assessment based on documentary evidence, from compensation proceedings under Section 71, which require a more elaborate adjudicatory process.Delay and finality were central to the outcome.The judgement observed: “Even if one can raise the facet of jurisdiction at any stage it is well settled that closed and concluded matters cannot be reopened on the premise that a subsequent judgement of a superior court has declared the law differently.”The chronology was also significant. The High Court noted that the developer waited nearly three years after that judgment before filing the present writ petition.The court also noted that another bench was already dealing with a petition filed by the homebuyer concerning the enforcement proceedings. In the circumstances, it was unwilling to exercise the High Court’s discretionary writ jurisdiction to reopen the dispute.According to Shruti Maniar, Partner, Solomon & Co, the Bombay High Court analysed the effect of the Supreme Court judgment of Newtech for this ruling.“Although, under RERA, the power to order a refund vests in the Authority, the Authority may delegate any of its powers to its officers under Section 81. An Adjudicating Officer, being an officer of RERA, is a judicial officer to adjudicate compensation, which is a judicial function, such an officer may also perform summary functions such as directing a refund, as was done in the present case,” Maniar tells TOI.“A Writ Jurisdiction being discretionary in nature should be applied sparingly. Since the developer did not challenge the original order within the prescribed limitation period, allowing it to attain finality and the Writ Petition being filed nearly three years after Newtech, without sufficient explanation for the delay, the Writ Court rightly refused to exercise its discretionary powers,” she explains.
Key takeaways from the judgement
According to Shruti Maniar, the three lessons from the judgement are:
- For developers, the message is one of procedural discipline. Jurisdictional objections and challenges to adverse RERA orders must be raised without any delay or laches.
- A subsequent change or clarification in the legal position cannot be a fresh cause to challenge orders that have attained finality.
- The ruling also offers reassurance to homebuyers that any person does not suffer on account of procedural irregularity as prescribed under Section 30(b) of the RERA Act and ensures that refund orders will not necessarily become unenforceable merely because of change in law on account of later judgment passed by a superior court.